Manufactured by Reynolds Building Systems, Inc.205 Arlington Drive Greenville, PA 16125 724-646-3775This manual is copyrighted. Under the copyright
Step 8 Assemble Front Wall Panels1. Install (6) six 72" wall studs between 2x4 - 10' top and bottom plates.2. Cut (2) two 2x4-6' board
Step 8 Assemble Front Wall ContinuedSiding ExtendsBelow HeaderCut EdgeButt Square EdgesTogetherCut EdgeTongue EdgeLAP Edge5. Locate a 16" x 77-1/
Step 9 Set Lower Walls1. Secure wall panels together at the corners. Use (4) four 10d coated nails per corner. Nailwall panels to the floor. Nail thro
Step 11 Install Rear Gable3. Install the rear gable on the back wall. The gable siding will extend over the 1x3 trim onthe lower wall. NOT behind the
3. Using 1-1/2" hanger nails, install the right hangers to the 2x6 tie plate.The top hanger flange should line up with the 'X' mark.Woo
1. Install the trusses over the 'X' marks. Install hanger to the opposite sideof the trusses. Secure truss to metal hangers using 1-1/2"
Notch Around Stud2'x4' Panel2'x4' PanelStep 14 Install Loft Floor1. Install a 4' x 4' OSB flooring panel between the si
10'x12'10'x16'Building LengthRoof Shingles 7 bdl. 10 bdl.Roof 'drip' Edge 6 pcs. 7 pcs.Material DescriptionBuilding Tip:
3. Cut and install a 2x3 block toclose off the opening at thebottom of the overhang.Step 16 Install Gable Overhang8" Soffit Panels1x4 Gable Trim4
Step 18 Install Doors & Hardware4. Before you fasten the hinges to the doortrim, temporarily prop the doors in theopening. Leave a space at the to
Tongue EdgeLAP EdgeTool ListHammer & Phillips ScrewdriverFraming Square & LevelHand or Circular SawAlways wear safety glasses when cutting or
Woodville 10'x 16' Barn kit Packing ListQty. Qty.4 Wall Plates 120 " 4 1x4 Gable Trim 47 1/2"8 Truss - Bottom Cords 116 1/4"
10' - 0" Building WidthNail the 2x4s to the 4x4runners to keep the 2x4frame from moving.Constructing Details for Deluxe Floor SystemDeluxe f
Wood Gusset with 2x4 BlockSet these trusses aside. DO NOT use trusses for assembling the roof gables.Step 1 Assemble Trusses2x4 Truss Half2x4 BlockTop
Siding Extends3/4" Below PlateTip; Lay 2'x4' OSB sheathing underthe studs to prevent gable studsfrom being knocked loose whennailing th
Siding Extends3/4" Below PlateStep 3 Assemble Front Gable1. Assemble another gable frame. Install a 36" long 2x4 between the wallstuds. If i
4. Assemble the loft doors. The loft door frames aretemporarily held together with corrugated fasteners,this is the back side of the door frame. Place
Step 6 Assemble Back WallSiding Extends 3/4" Below PlateCut EdgeLAPTongue EdgeTop PlateWall Stud3-1/2"56-1/2" Tie Plate56-1/2" Tie
8. Repeat steps to assemble another sidewall.AACCXXXXBBXX23-1/4"48" Wall PlateXXXXXXXXXX1. Gather (4) four 2x4s that were removed from the s
Komentarze do niniejszej Instrukcji